Common-area LED retrofit
Harbor View Apartments · In progress
On the crew calendar: Apr 20, 2026 – May 15, 2026
20 crew days.
Scope and contract are out of sync
Current scope totals $44,040 price / $25,840 cost (41.3% margin). The contract is set to $48,500 with a $31,200 budget.
Financial snapshot
Contract value
$48,500
Budgeted cost
$31,200
Estimated margin 35.7%
Actual cost to date
$22,130
144 labor hours logged
Projected profit
$17,300
Margin 35.7%
Budget consumed
$22,130 spent of $31,200 (71%)71%
Budget consumed: Project details
- Client
- Harbor View Apartments
- Stage
- In progress
- Service type
- Lighting
- Site address
- 120 Harbor Rd, Westerville, 43081
- Crew days
- 20
- Start date
- Apr 20, 2026
- Target completion
- Jun 15, 2026
Description
Replace hallway, stairwell and parking lighting with LED fixtures and occupancy sensors.