Common-area LED retrofit

    Harbor View Apartments · In progress

    On the crew calendar: Apr 20, 2026 – May 15, 2026
    20 crew days.
    Scope and contract are out of sync
    Current scope totals $44,040 price / $25,840 cost (41.3% margin). The contract is set to $48,500 with a $31,200 budget.

    Financial snapshot

    Contract value
    $48,500
    Budgeted cost
    $31,200
    Estimated margin 35.7%
    Actual cost to date
    $22,130
    144 labor hours logged
    Projected profit
    $17,300
    Margin 35.7%
    Budget consumed
    $22,130 spent of $31,200 (71%)

    Project details

    Client
    Harbor View Apartments
    Stage
    In progress
    Service type
    Lighting
    Site address
    120 Harbor Rd, Westerville, 43081
    Crew days
    20
    Start date
    Apr 20, 2026
    Target completion
    Jun 15, 2026
    Description
    Replace hallway, stairwell and parking lighting with LED fixtures and occupancy sensors.