Common-area LED retrofit
Harbor View Apartments · In progress
Budget vs. actual
Budget comes from scoped costs by category
Category | Budget | Actual | Remaining |
|---|---|---|---|
Labor | $8,800 | $7,920 | $880 |
Materials | $17,040 | $13,320 | $3,720 |
Equipment | $0 | $890 | $890 over |
Unallocated budget | $5,360 | $0 | $5,360 |
Total budget
$31,200
Total actual
$22,130
Remaining
$9,070
Spend by category
$0
$5,000
$10,000
$15,000
$20,000
Budget
Actual
Cost entries (5)
Labor, materials, rentals, subs, and fees charged to this job
Date | Description | Category | Vendor | Hours | Amount | |
|---|---|---|---|---|---|---|
May 7, 2026 | Install crew week 2 | Labor | — | 64 | $3,520.00 | |
Apr 30, 2026 | Install crew week 1 | Labor | — | 80 | $4,400.00 | |
Apr 28, 2026 | Scissor lift rental | Equipment | Sunbelt Rentals | — | $890.00 | |
Apr 22, 2026 | Occupancy sensors | Materials | CED Supply | — | $1,920.00 | |
Apr 22, 2026 | LED fixtures - first shipment | Materials | CED Supply | — | $11,400.00 |