Whole-home insulation & air sealing
Riverside Residence · Completed
On the crew calendar: Mar 2, 2026 – Mar 4, 2026
3 crew days.
Scope and contract are out of sync
Current scope totals $7,460 price / $4,040 cost (45.8% margin). The contract is set to $12,400 with a $7,600 budget.
Financial snapshot
Contract value
$12,400
Budgeted cost
$7,600
Estimated margin 38.7%
Actual cost to date
$5,250
52 labor hours logged
Final profit
$7,150
Margin 57.7%
Budget consumed
$5,250 spent of $7,600 (69%)69%
Budget consumed: Project details
- Client
- Riverside Residence
- Stage
- Completed
- Service type
- Insulation
- Site address
- 9 Riverside Dr, Grandview Heights, 43212
- Crew days
- 3
- Start date
- Mar 2, 2026
- Target completion
- Mar 20, 2026
Description
Attic blown-in insulation to R-49 plus air sealing.