Kitchen & storefront LED retrofit

    Oak Hill Bakery · Scheduled

    On the crew calendar: Oct 6, 2026 – Oct 7, 2026
    Nearby jobs had no open crew capacity close by — booked the earliest open slot.

    Financial snapshot

    Contract value
    $9,800
    Budgeted cost
    $6,100
    Estimated margin 37.8%
    Actual cost to date
    $0
    No labor hours logged
    Projected profit
    $3,700
    Margin 37.8%
    Budget consumed
    $0 spent of $6,100 (0%)

    Project details

    Client
    Oak Hill Bakery
    Stage
    Scheduled
    Service type
    Lighting
    Site address
    18 Bridge St, Dublin, 43016
    Crew days
    2
    Start date
    Oct 6, 2026
    Target completion
    —
    Description
    Replace kitchen fluorescents and storefront signage lighting.